Hawick Sewer Improvement Project

Update February 2017:

All works are now complete with the final resurfacing of Duke Street being completed  on Thursday 9th February and all generators have been switched off and removed from site. Both Mansfield Road and Duke Street are now open to through traffic

Key Project Facts:

This £1.2m project at Duke Street, Hawick in Scottish Borders was to replace the damaged public sewer during the storms of December 2015. This will also help alleviate flooding during periods of heavy rain and storms.

The work involved replacing the damaged section of sewer which crosses the River Teviot at Mansfield Road and Duke Street / Glebe Mill Street in Hawick.  This will bring a number of important benefits to the community.

The work was completed in collaboration with Scottish Borders Council and was carried out by our contractors Morrison Construction.