Open day in Helensburgh
What we're doing
We held an open day on 25 June 08 to show our customers our plans for our sewage infrastructure and other projects
Amount invested
About £4.5 million on 10 separate projects in Helensburgh
Start Date
January 2008, others started in late summer 2008
End date
Completed by the end of 2009
Partners
GMJV for Scottish Water Solutions Hanover Pumping Station, Middleton Drive and Craigendoran Avenue
Affected Areas
Hanover Pumping Station: should be complete by the end of the summer 08.
Colgrain and Craigendoran Pier started from June 08 onwards
Middleton Drive and Craigendoran Avenue are also affected
Lomond Street, George Street, Charlotte Street, Glenfinglas Street: September 2008
Work on the streets near the centre of town was delayed to minimise disruption during the summer holidays.
To check ongoing work, call our contact centre on 0845 601 8855