skip to content

12 February 2010

Loch Ryan project - further works

Not only will we be constructing new pipelines, pumping stations and a waste water treatment works but a sewer study is also going to be carried out in Stranraer to make sure we understand how the existing pipes are operating.

This element of the project will be carried out by the main contractor, when they are appointed, and is essential to ensure a smooth transition when the new works are operational.

The study should not involve disruption to roads or footpaths in Stranraer.


Cairnryan Pumping Station approved

4 February 2010

Approval of the Cairnryan pumping station is another step forward for the Loch Ryan project, which will facilitate economic growth in Stranraer and surrounding communities while protecting the delicate shellfish waters the area is famous for.
 
Scottish Water will fully communicate with the local community on the design and configuration of the pumping station at Cairnryan in the months to come. Our project team is aware of the concerns of the community and is working to reduce the impact on the waterfront views from Cairnryan and to construct a mutually agreeable facility. 
 
We have plans to involve the community in a variety of ways with the Loch Ryan project in the coming months and years in addition to the open events, briefing sessions, e-letters and media work we have performed to date.


Scottish Water: Loch Ryan Strategic Solution: E:Letter Nr. 05

Port Rodie Pumping Station Planning Application

The planning application for Scottish Water’s Pumping Station located in Port Rodie was approved at the Dumfries & Galloway Committee Meeting in Stranraer on Wednesday 6th January 2010.
 
The Port Rodie facility is a key part of the proposed Loch Ryan Project which will remove the permanent discharge of waste water into Loch Ryan - home to sensitive shellfish waters which are Scotland’s only natural native oyster beds.

Audit Scotland Report

An extract from “Protecting and Improving Scotland’s Environment” Report issued by Audit Scotland on 14th January 2010 follows:

Between 2003/04 and 2008/09, Scottish Water invested £292 million to meet the requirements of the Urban Waste Water Treatment Directive. This has enabled progress towards the directive’s goal of all urban areas having appropriate waste water treatment collection systems by 2005. When Scottish Water was formed in 2002, a quarter of waste water treatment collection systems in Scotland were not appropriate. By the end of 2009, this had reduced to one per cent. All but one urban area in Scotland are scheduled to have an appropriate sewage collection system by the end of 2011, with the final one - Loch Ryan, Stranraer scheduled for completion in 2014.

Tender

The Invitation to Negotiate (ITN) tender phase has entered Stage 3 and contractor returns are expected in early February 2010.   A contract will be awarded in late June/ early July.

Land Purchase

Leswalt and Cairnryan land purchase negotiations are already underway with the local landowners and P&O Ferries respectively.

Port Rodie negotiations have re-started after the planning approval announcement.

Planning

Cairnryan planning application was deferred until February 3rd with a request for further information required to satisfy Councillors that the proposal met residents concerns as expressed against the initial application.

A decision is expected on Leswalt in the coming weeks after technical queries are addressed with SEPA.

Investigations

Marine site investigations in Loch Ryan and in the North Channel are now complete.

Some minor works are still to be undertaken on land based site investigations.

Community Forum

As the project gets nearer to starting we intend establishing a Community Forum which will be made up of Scottish Water project and appointed delivery partner team members along with invited representatives from local organisations.  The Forum will run up until six months after completion of construction and landscaping.  We are currently working on the details of attendees, frequency, venue and time of meetings and we hope to be able to confirm the details in the next couple of months.  Scottish Water will provide meeting facilities and will chair the meeting.  We will also provide a Minutes Secretary who will provide draft Minutes to all attendees and organisations represented.  Additional distribution of minutes will be agreed by members of the Community Forum. 

We hope the Community Forum will provide an opportunity for close co-operation, promoting open communication between participants whilst acknowledging the independence of each organisation represented to act according to its own constitution and remit.

We will continue to provide regular press statements and E-Letters with project updates. We will also hold further Open days to give as many people as possible the opportunity to communicate with the project team.

We want to hear from you

Updates will always be posted on our website when available.  If you would like to contact Scottish Water about the Loch Ryan Strategic Solution project, you can:
 

•  Phone:                       Customer Helpline:               0845 601 8855
•  E_Mail:                       LochRyan@scottishwater.co.uk
•  Write to:                      Project Manager, Loch Ryan Scheme, Leven House,
   Balmore Road, Glasgow. G22 6NU.
•  Visit our website:        www.scottishwater.co.uk/lochryan
 
•   If you would prefer not to receive this E:Letter in the future, please advise by e-mailing ‘lochryan@scottishwater.co.uk’ with subject heading ‘E:Letter unsubscribe’
 
Finally, thank you for taking time to read through our latest E:Letter.  We’d appreciate your views on how useful you find this and if you can think of any individual or organisation that you think may like subsequent E:Letters, then please let us know.
 
Scottish Water is committed to engaging our customers in the Loch Ryan area in a meaningful, clear conversation.  We hope that this E:Letter continues to demonstrate this commitment.
 
Thank you

Stephen Hepburn
Project Manager
Capital Delivery Investment, Scottish Water


Latest News

7 December 2009

Scottish Water awaits decision from planning committee

Scottish Water accepts that the planning committee wish to defer a decision on the planning application for Port Rodie Pumping Station until 7th of January. We respect that they would like to see more information regarding the waterfront regeneration proposals which are currently being drafted.

Helen Lennox, head of corporate affairs, Scottish Water, said:

“The planned Loch Ryan waste water project is a crucial component in the regeneration and future prosperity of Stranraer. Stranraer is one of the last major towns in Scotland to receive a modern waste water infrastructure that will protect the natural environment and contribute towards Loch Ryan’s compliance with the EU Urban Waste Water Treatment Directive and SEPA standards for shellfish waters.

“Scottish Water has been in full consultation with the council planners and the regeneration group, as well as holding open events to brief the local community on our plans. Upgrading the waste water network will provide a fundamental resource that supports the collective aspirations of the local community and enhance their quality of life.

“We trust the planning committee will recognise the profound importance of our project in the future development of Stranraer.”



18 November 2009

Read the Cairnryan Pumping Station questions and answers

4 November 2009

27th October Open Day FAQs now on the website.


2 November 2009

Scottish Water – information event discusses Cairnryan project

Thanks to local people for attending the information evening at the Craignelder Hotel on 27th October. The event was well attended with over 20 residents coming along to share their views.

The proposed project will replace the current waste water treatment works in the village with a pumping station, enabling waste water from the town to be pumped to the new planned waste water treatment works at Smithy Hill.

Loch Ryan will no longer be the discharge point for the region’s waste water – waste water facilities at Leswalt, Kirkcolm, Stranraer and Cairnryan will be modified to move waste to the new works at Smithy Hill and away from Loch Ryan by 2012. The treated waste water will be pumped to an outfall pipe in the Irish Sea near Larbrax.

The existing tanks at the Stranraer works will be adapted to hold storm water in times of heavy weather, which will offer relief for the system and reduce the risk of local flooding.

The new treatment process will consist of two stages of treatment – an improvement on the single stage process currently in place at Stranraer. The overall cost is currently estimated at around £25million.

Stephen Hepburn, Project Manager, said: “Overall the event was very productive and Scottish Water is committed to accommodating the concerns of the Cairnryan residents where possible. 

“We are aware of the strength of feeling in relation to the fencing and are looking to reduce its impact or remove it all together. 

“It was very encouraging to hear that the majority of residents attending agreed with the principle of our plans to improve the water quality of Loch Ryan.”

Scottish Water recognise that the pumping station that will replace the existing waste water treatment works gives rise to concerns and will work to find a way forward which accommodates the wishes of the local community. 

Andy Wilson, Regional Communities Manager, said:

“The fact that local residents took the time to come and talk to Scottish Water was greatly appreciated and this constructive dialogue will be used to amend the current planning application.”

We are drafting revised plans in terms of fencing and the pumping station structure that will be submitted to the Planning Authority shortly.

If you want more information about the project, call the Scottish Water contact centre on 0845 601 8855 or write to Scottish Water at PO Box 8855, Edinburgh, EH10 6XH.


23 October 2009

Mollie B Boat

Deploying tidal monitoring equipment at Port Rodie using the boat Mollie B.


Loch Ryan E:Letter 8 October 2009

Current Position

Scottish Water are currently within the Invitation To Negotiate (ITN) tender phase for a Design and Build partner.  ITN Stage 1 has been processed and 5 companies given approval for ITN Stage 2.  The appointment of a delivery partner is a critical programme item.

SEPA have accepted SW’s programme for the Strategic Solution and are actively involved in monitoring our progress.

This E:Letter, along with other information, drawings and photographs, is be posted on our project website at www.scottishwater.co.uk/lochryan as and when any new information becomes available.
 
Loch Ryan (New) WWTW

This application was lodged with Dumfries and Galloway Council on 18th March 2009.  Planning permission for the Waste Water Treatment Works site was obtained in June 09 and the land negotiations are concluded, subject to missives.

Planning Approval was granted on 29th May 2009.

Cairnryan Pumping Station

Planning agreed, planning application was lodged submitted on 25th September 2009.  View the Cairnryan pumping station planning applications on this website.

Land requirements have been assessed and initial contact has been made with the land owner -in this instance P&O European Ferries.

Leswalt Pumping Station

Planning requirements have been reviewed and final design layout agreed, planning application was lodged submitted on 25th September 2009.  View the Leswalt Pumping Station planning application here.

Land requirements have been assessed and initial contact has been made with the land owner - in this instance a local farm owner.

Kirkcolm Pumping Station

Requirements have been reviewed and subject to final design layout, application will be lodged in the near future.  However, this has the potential to fall into Permitted Development.

Port Rodie Transfer Pumping Station

The Planning Application was submitted in March 2009.  As with the other planning applications, Scottish Water land agents have approached D&G Council with a view to the purchase of the additional land noted in the planning application.

Marine Site Investigation

Investigations are planned for two locations;  Larbrax (North Channel of Irish Sea) and Port Rodie in Loch Ryan.

Works have started on geo-physical mapping, bathymetry and magnetometry to confirm dispersion through water depth and tidal movements both desktop and measured.

The undefined length of the sea outfall at Larbrax requires a water based geo-physical survey to confirm water depth, tidal movements and surface water movements which could be used to confirm dispersion and therefore length of the outfall, however, the survey would require to be completed by the end of September to allow enough light for the dye and drogue tests.

Investigations commenced on 20th September 2009 for an estimated 3 week duration.

Land Site Investigation

Investigations are planned for all areas, Loch Ryan WwTW, Port Rodie and along the full length of the pipeline as currently proposed.

Proposed investigations are all intrusive through a variety of methods; borehole, slit trench or trial pit to allow definition of bearing strata, material type, hazard identification, service location/confirmation and ultimately for finalisation of pipeline route.

Section 48(1)(a) notices have been issued to approximately 35 landowners, between the end of March 2009 and the middle of June 2009, to allow the full extent of the investigation to begin.

Land investigations are planned to commence in November 2009.

Other Information

The Loch Ryan Shellfish Company has written a letter of support to SW for the current proposals. 

The Project Team are also in discussion with Transport Scotland in relation to the proposed upgrades to the A77 (Cairnryan to Stranraer).

The downturn in the construction market is well documented and the timing of the current programme has socioeconomic benefits for both local and national workforce.


We want to hear from you

If you would like further information about the proposed Loch Ryan improvements then please contact us via the methods shown below:

write to:
Project Communications
Loch Ryan Improvement Scheme
Scottish Water
PO Box 8855
Edinburgh
EH10 6XH

phone:
Customer Helpline 0845 601 8855, quote the Loch Ryan project

email:
lochryan@scottishwater.co.uk

 

Scottish Water: Loch Ryan Strategic Solution: E:Letter Nr. 04

Overview/ Recap

The water in Loch Ryan needs to meet the requirements of the Urban Waste Water Treatment Directive and standards for Shellfish Waters. These strict European regulations have resulted in cleaner beaches and rivers across Scotland, with Stranraer and surrounding towns amongst the last to adopt these standards. Recreational watercourses and beaches are vital to tourism and the economy of local communities - Loch Ryan is no exception.

Our scheme has the support of our environmental regulator SEPA and the Scottish Government. Youc an find more information on how the proposed new waste water process will work on this website.

Scottish Water’s Loch Ryan project aims to give the town of Stranraer and the smaller communities which surround Loch Ryan the same quality of waste water treatment as the rest of Scotland.

The multi-million Loch Ryan project is designed to:

• improve the environment and water quality of Loch Ryan;
• enable growth in the area; and
• enhance the quality of life for local people.

Our project team are dedicated to delivering a project which improves the environment around Loch Ryan and positively contributes to the regeneration of the waterfront as a great place to live, work, play and do business.
Current Position – Port Rodie Pumping Station

Scottish Water currently awaits a decision from the planning committee and accepts that they wish to defer a decision on the planning application for Port Rodie Pumping Station until 7th of January 2010.   We respect that they would like to see more information regarding the waterfront regeneration proposals which are currently being drafted, prior to making their decision.

The planned Loch Ryan waste water project is a crucial component in the regeneration and future prosperity of Stranraer.  Stranraer is one of the last major towns in Scotland to receive a modern waste water infrastructure that will protect the natural environment and contribute towards Loch Ryan’s compliance with the EU Urban Waste Water Treatment Directive and SEPA standards for shellfish waters.

Scottish Water has been in full consultation with the council planners and the regeneration group, as well as holding open events to brief the local community on our plans. Upgrading the waste water network will provide a fundamental resource that supports the collective aspirations of the local community and enhance their quality of life.

We trust the planning committee will recognise the profound importance of our project in the future development of Stranraer.

Tender

The Invitation to Negotiate (ITN) tender phase has entered Stage 3 and contractor returns are expected in early February 2010.

Land Purchase

Land purchase negotiations are underway at Port Rodie, Leswalt and Cairnryan and should be complete early in the New Year.

Planning

Planning applications for Cairnryan and Leswalt are anticipated to be approved in January and February 2010 respectively.

Investigations

Marine site investigations in Loch Ryan and in the North Channel are now complete.

Land based site investigations have been undertaken through November, at all major project centres and along the route of the 30km of pipeline for the project.  These works are stopped for the Christmas break and are substantially complete, with a potential for some minor works in the New Year.

Other projects in Stranraer:  A Water Quality Project is underway to assess the impact from intermittent discharges.

We want to hear from you
 
Updates will always be posted on our website when available.  If you would like to contact Scottish Water about the Loch Ryan Strategic Solution project, you can:
 

•  Phone:                       Customer Helpline:               0845 601 8855
•  E_Mail:                       LochRyan@scottishwater.co.uk
•  Write to:                      Project Manager, Loch Ryan Scheme, Leven House,
   Balmore Road, Glasgow. G22 6NU.
•  Visit our website:        www.scottishwater.co.uk/lochryan
 
•   If you would prefer not to receive this E:Letter in the future, please advise by e-mailing ‘lochryan@scottishwater.co.uk’ with subject heading ‘E:Letter unsubscribe’
 
Finally, thank you for taking you time to read through our latest E:Letter.  We’d appreciate your views on how useful you find this and if you can think of any individual or organisation that you think may like subsequent E:Letters, then please let us know.
 
Scottish Water is committed to engaging our customers in the Loch Ryan area in a meaningful, clear conversation.  We hope that this E:Letter demonstrates this commitment.

Stephen Hepburn
Project Manager
Capital Delivery Investment, Scottish Water


21 September 2009

What's planned?

Scottish Water is proposing an investment to dramatically increase the water quality in Loch Ryan’s renowned shellfish waters.  The project will deliver a long-term solution to the treatment of waste water generated within the catchments of Stranraer, Cairnryan, Kirkcolm and Leswalt. 

This scheme has been many years in planning and involves a number of co-ordinated infrastructure improvements and additions.  The overall aim of the project is to remove continuous discharges from the main communities around the Loch which will improve the quality of both shellfish and leisure waters.  We have been liaising closely with SEPA (Scottish Environmental Protection Agency) to ensure the project also complies with environmental standards.

This is our proposed solution:

1. New WWTW (near Leswalt) to treat flows from Stranraer, Cairnryan, Kirkcolm and Leswalt.
2. Construction of new Pumping Station to replace Port Rodie’s WWTW.
3. Provision of underground storm pumps at Port Rodie and the possible extension of the existing continuous outfall which would become a storm outfall. The existing emergency outfall will be abandoned.
4. Transfer pipelines directing pumped flows from the 4 locations to the new works.
5. Treated flows transferred to the North Channel (Larbrax Shore Area) via a new pipeline and long sea outfall.
6. Hydro scheme to recover energy – location yet to be confirmed but expected to be near Larbrax
7. Approximate line of Emergency Outfall.

Loch Ryan

As the project develops, Scottish Water will work closely with the four main communities involved in this scheme.

Traffic management

Traffic management will be used on the main pipeline routes, which will include the A77 (from Cairnryan to Stranraer), through Stranraer and the A718 towards Leswalt. Construction work is due to begin in spring/summer 2010.

This handout is just one part of a detailed information campaign to keep customers around Loch Ryan updated on the benefits being delivered in the area.  We will provide further information on our plans via information events, press statements, newsletters and our website.

Port Rodie, the improvements in detail…

1. A main element of the project will be creation of a new waste water treatment plant (WWTW) being built near Leswalt. It will discharge treated effluent into the Irish Sea, near Larbrax Bay.

2. In addition, the existing Port Rodie WWTW will be modified to become a pumping station which will pump wastewater to the new treatment works. The current Port Rodie building will be demolished.  A modern replacement will be constructed, Scottish Water has liaised closely with Dumfries & Galloway Council to ensure the designs will fit in with future waterfront developments.

3. Once the changes are completed, the existing Port Rodie site will deliver further benefits when it is modified to provide storm storage. This is essential, as it will reduce the risk of the Stranraer network having to use storm overflow contingencies at times of heavy rainfall. 

4. A host of smaller facilities will also form part of the project. These will include pumping stations at  Cairnryan and Kirkcolm which will allow waste to be transferred to the new Loch Ryan WWTW.

5. A series of transfer pipelines will be laid so the waste can be transferred to the new treatment works.  While the locations are fairly remote, these new sections of pipeline will be in places as close as possible to the roads leading in and out of the areas.

We will need planning permission from Dumfries and Galloway Council in order to carry out some of the proposed work.  However, we can carry out the other improvements under the Sewerage Scotland Act. The improvements would be carried out in the various packages as detailed above.

The construction phases will all be completed by 2012 as shown on the project timetable below:

Loch Ryan timetable 0909

9 July 2009

Planning Applications

Loch Ryan Planning Applications have been submitted to Dumfries and Galloway Council, on 18th March, for both the new Treatment Works at Smithy Hill near Leswalt and the new Pumping Station at Port Rodie in Stranraer.

Dumfries and Galloway have approved the application for the development at Smithy Hill and have asked for further supporting information before determining the application for Port Rodie.

We would like to invite you to view the planning applications we have lodged, making any views or suggestions you may have known to the local planners. You can view both the planning applications and the approval here.

Scottish Water attended the last stakeholder workshop with the Waterfront Development Consultants on 13th May and now awaits, like everyone else, the outcome of the public consultation and the reveal on the Waterfront Masterplan.<

The project team have recently met with Westminster MP Russell Brown and again can report a very good level of support for the project and the Waterfront Development in general.

Liaison with Local Residents and Community

We have now spoken to around 70% of the landowners along the route of the pipeline, focussing on those who will be affected by the proposed site investigation works.
Our next phase is to speak to all landowners who will be affected by the installation works, with the first discussions taking place in mid to late July.

Site Based Activities

Land based site investigations were due to start at the end of June but are now more likely to start around mid July.

The project team are in continued discussion with a number of landowners who have raised concerns over the work to try to reduce the impact locally or to agree an alternative to the works proposed.  Through these discussions information, that is useful to the project, is surfacing and like Golf you can’t beat local knowledge. 

Other information being unearthed relates to the history of the peninsula with particular reference to the Army Camp and Sunderland Sea Plane Airfield that were sited near Kirkcolm.

Marine site investigation should be underway by mid July with barges visible at either Broadsea Bay or in the Port Rodie/ Stranraer Harbour area.

Making Contact

Updates will always be posted on our website when available.  If you would like to contact Scottish Water about the Loch Ryan Strategic Solution project, you can:

Phone our Customer Contact centre: 0845 601 8855

Email: LochRyan@scottishwater.co.uk
Write to: Project Manager, Loch Ryan Scheme, Leven House, Balmore Road, Glasgow. G22 6NU.

If you would prefer not to receive this E:Letter in the future, please advise by e-mailing ‘lochryan@scottishwater.co.uk’ with subject heading ‘E:Letter unsubscribe’

Thanks, Stephen Hepburn, Project Manager, Loch Ryan WWTW

5th June 2009

Dumfries & Galloway Council granted approval of the new Waste Water Treatment Works proposed at Smithy Hill near Leswalt.

Keep checking this website for further developments in the project.

6 May 2009

Our first e:newsletter!
 
We will update you every month on the progress of the pre- construction activities being undertaken during this phase of the project.
 
Planning Applications
 
Loch Ryan Planning Applications have been submitted to Dumfries and Galloway Council, on 18th March, for both the new Treatment Works at Smithy Hill near Leswalt and the new Pumping Station at Port Rodie in Stranraer.
 
Dumfries and Galloway have acknowledged and verified the applications which have already been advertised in the Stranraer and Wigtown Free Press on 25th March 2009.
 
Discussions regarding the application are ongoing with Dumfries and Galloway Council Planning Department as well as the Waterfront Development Consultants, including Scottish Water attendance at the next Waterfront Open Day to be held in Stranraer on 13th May.
 
You can view these plans, and should you have any concerns or thoughts, you may raise these with the Local Planners.   The planning application has been put up onto our website.

Meeting MSPs
 
The project team have recently met with both Alex Ferguson and Alasdair Morgan, the MSPs for the region, to discuss the planning applications.  Both meetings ended very positively with further shared knowledge of aspirations and expectations, and recognition that Scottish Water are potentially providing the infrastructure support for the future development of the Waterfront.
 
Liaison with Local Residents and Community
 
It is the intention of the project team to try and visit all of those landowners along the route of the pipeline where access is required to complete the surveys discussed further below.  It is hoped that we can discuss the activities required in order to complete the surveys at a time convenient to the specific landowners. 
 
The Project Team are also setting up a meeting with all of the local Councillors to update them on the progress of the project and to discuss any issues that they may have.  Details of this meeting will be issued via future E:Letters and on the website.

Our next step will be to arrange visits to the local Community Councils and any local stakeholders.

Site Based Activities

The project is due to start construction in the Spring of 2010, so there won’t be a lot of activity until then.  However, planned site surveys and investigations will be ongoing from now until the Spring of 2010.

Land Based Topographic Surveys are well underway.  These involve the survey of position, height and gradient of the surface of the landscape including features such as properties, hedges, fences, roads, footpaths, manholes, hydrants, bridges etc. over a 30m wide corridor centred on the proposed route of the pumping main pipeline.

The Topographic surveys are substantially complete on Leg 5 of the Scheme pumping mains, an overview of which can be seen by reading our 8th April update. 

Further topographic surveys will be undertaken, in the immediate future, between the new Waste Water Treatment Works (WwTW) site and Loch Ryan itself, near to Stranraer Golf Club.

Land Based Site Investigation

On completion of the Topographic Surveys, as detailed above, it is the intention of the project team to start sub surface surveys to determine the suitability of the existing material through which the pipeline will be laid and to determine the nature and depth of the rock strata below the pipeline.

This activity will be required along the entire length of the 30km of pipelines;  from Cairnryan to Stranraer, from Kirkcolm and Leswalt to the new WwTW and from the new WwTW to the long sea outfall at Broadsea Bay, Larbrax.   Section 48 notices will be issued during the next few weeks to allow the boreholes and trial pits to start by the middle of May.

Marine Site Investigation - Marine Site Investigation includes;  boreholes on the sea bed along the proposed route of the long and short sea outfall pipes.  Tidal movements, in terms of currents both surface and sub surface and tidal heights, minimum, maximum and mean.

Applications for the Marine Site Investigation for the long and short sea outfalls at both Broadsea Bay and Port Rodie, have been approved by the Crown and should be advertised in the Stranraer and Wigtown Free Press in the very near future with a view to work starting in May of this year.

We want to hear from you

Updates will always be posted on our website when available.  If you would like to contact Scottish Water about the Loch Ryan Strategic Solution project, you can:

Customer Helpline 0845 601 8855

EMail:LochRyan@scottishwater.co.uk
Write to Project Manager, Loch Ryan Scheme, Leven House,Balmore Road, Glasgow. G22 6NU.

If you would prefer to receive th E:Letter directly, please by e-mailing ‘lochryan@scottishwater.co.uk’ with subject heading ‘E:Letter unsubscribe’


28 April 2009

View the latest planning documents


8 April 2009

Topographic of Loch Ryan

Topographic surveys on one of the pipe legs from Leswalt to Larbrax.

Loch Ryan Project Team

Photo caption: Stephen Hepburn (left) and Andy Wilson (second from left) take local men Mr Burns (second from right) and Mr Irving (right) through the plans for the project.

18 March 2009

Scottish Water lodged the applications for planning for both Port Rodie and Loch Ryan WwTW in a meeting with Dumfries and Galloway Council at their offices in Stranraer.

Scottish Water open day in Stranraer a success

More than 50 local people came to see the proposed plans for a new waste water solution for the area at the John Niven Centre in Stranraer on Thursday 19th February.

In addition to large posters of plans on the wall, there was also a PowerPoint presentation that showed a draft design for the new pumping station at Stranraer and handouts (listed on the right) for local people to take away.

The Scottish Water project team also met up with Alex Fergusson MSP to give him a briefing on the plans before opening up to the public.  Mr fergusson said:

 

"I was pleased to be able to attend this briefing and be updated on Scottish Water's plans for Loch Ryan, which are extensive and thorough. The clear winner will be the waters of Loch Ryan which, given the potential for the redevelopment of Stranraer Harbour Waterfront, can only be a very good thing.

“However, this is a large scale engineering project which will, inevitably, cause a degree of disruption to the communities involved.

I am heartened by Scottish Water's determination to ensure a proper consultation process with those communities and also to liaise with the Council and others, such as Stena and Transport Scotland, who will be undertaking major projects at the same time, in order to minimise that disruption.

That must be the aim, and if it is achieved, the outcome will be very well worth it."

From 2pm until 8pm the project team was on hand to accept members of the public, and they spoke to a range of people including landowners, developers, farmers and local residents.

Stephen Hepburn, project manager, Scottish Water, said:

“This was a fantastic event and really enabled us to interface with the community, allowing them to discuss the project directly with the engineers and designers.

“The proposed solution currently involves transferring waste water flows via a network of pumping stations to a new waste water treatment works near Smithy Hill. This will then pump the treated waste to an outfall pipe in the Irish Sea near Larbrax.

“This will end the current practice of permanently discharging waste water into Loch Ryan, and will enable us to convert the current works at Stranraer into storm water storage tanks. Pumping stations at Cairnryan, Leswalt and Kirkcolm will pump the waste from these communities to the new works, creating a modern waste water treatment process for the area.

The new treatment process will consist of two stages of treatment – an improvement on the single stage process currently in place at Stranraer. The overall cost is currently estimated at around £20million.”

Share this page:

Follow us on YouTube at scottishwaterfilm  Post this story to Facebook  Follow us on Twitter  Post this story to Del.icio.us Post this story to Digg  Post this story to reddit Post this story to stumbleupon 


Report A Leak

Always serving Scotland