Roadworks Generic

Scottish Water are installing a new sewer pipe on Haugh Road, Dalbeattie.

This work is to upgrade the sewer network to help mitigate sewer flooding to a number of properties.

Work will start at Haugh Road on Monday 4th March and will last approximately 6 to 7 weeks. 

This work will require temporary traffic management in order for the team to work safely. We ask road users to please take care while following all signage, and diversion routes in place. Pedestrian access will be maintained throughout. 

  • Phase 1 – one lane will be closed on Haugh Road, and traffic will be managed with 3 way temporary traffic lights. (estimated 4-5 weeks)
  • Phase 2 – estimated for 1st April, Haugh Road will be closed for the remainder of the project, (estimated 2-3 weeks)

We thank those affected for their patience and understanding while we carry out this essential work.