Latest Updates - January 2024

We have completed the sewer repair and Murano Place and Albert Street are fully open following the road reinstatement. 

As part of our project completion learning and reflection, we ask that you will spend 5 minutes to complete our survey on how well we collaborated with you throughout this journey - Feedback Survey

Project Overview

This investment project, which is underway on Murano Place, Edinburgh is to repair a damaged sewer to improve our waste water network and ensure we continue to deliver resilient waste water services for our customers in the street.

The project is being delivered by our delivery partner, Mackenzie Construction Ltd. 

A reminder that local businesses are open as usual while essential works are under way:

  • Tepuy Coffee 
  • Sicillian Pastry Shop
  • U Save Shop
  • Albert St Butchers
  • Juiding Chinese Takeaway
  • Belle Chexeux
  • John Redpath Electical
  • Word of Mouth Coffee
  • Santosa Wellness Centre + Cafe
  • Rajahs Supermarket

At a Glance

  • Murano Place is closed and there is no vehicle access to Leith Walk from Albert Street
  • General working hours will be Mon-Fri 8am-4.30pm
  • Bin collections will continue as normal with the support of site workers.

Open business signs

Signs erected at the end of Albert Street from Leith Walk to inform passerbys that businesses are operating as nomal.

Arial shot of progress on Murano Place

Arial shot of working area within Murano Place and Albert Street.

What we are doing

We are taking care of the waste water services by replacing the damaged sewer network in Murano Place to reduce the risk of localised flooding and stabilise the road.

Due to its location and close proximity to existing properties and the depth of the sewer, which is approximately 3.5 to 5 metres below ground level, this is a complex repair which will take time to repair.

General working hours will be Mon-Fri 8am-4.30pm however there may be occasions when we need to work out with those hours (including weekends) to complete a section of works.

Murano Place will be closed during the works and there is no access to Leith Walk via Albert Street.

Why we are doing it

We initially investigated a sewer blockage and depression in the road in January 2022. We carried out a sewer inspection with cameras and found that the sewer which ranges from 3.5m to 5.4m deep had collapsed in at least 4 places, over a length of 100m on Murano Place.

Mains generated temporary over pumping was installed to bypass the section of sewer below the depression on the carriageway and ensure properties waste was removed as normal.

Ground conditions have proven difficult as we discovered sink holes and voids under the carriageway at least 2.5m in depth. Ground water became evident and running sand under the roadway. Due to this, we engaged with a Geotechnical Engineering Consultant to carry out further ground testing.

Ground investigations have concluded, and a plan has been designed for the replacement for the sewer.