River Kelivn Kelvingrove

This has been planned for during the winter/spring season when the footfall is lower in the park.

Location    Start Date  Duration  Type of work
Near Kelvingrove Bandstand  February 2019  5 months   Install chamber, pipework and headwall

A section of footpath near the bandstand is required to be closed throughout the duration of the works for the safety of the public. This Poster has more details about the footpath closure.

We shall reinstate the area with grass seed and plant trees once it is completed.

We have been working with Hillhead Primary School and Kelvin Park Early Years. We shall be setting competitions and presentation to them during February 2019 to advise the students about the project.

The school have voted for a fox to be carved from a tree that is required to be removed as they have a family of foxes that visit the school. Kelvin Park Early Years have voted for a Kingfisher.