Near 317 North Woodside Road Glasgow

We carried out investigation work here in 2018. We will write to the local residents prior to the project starting.

Location Start date Duration Type of work
Near 317 North Woodside Road Glasgow 2nd March 2020 5 months

Install chamber and pipework

 

Northwoodside Road
Investigation work stage during the Summer 2018

In August in 2018, we carried out investigation works on the existing sewer network (located in North Woodside Road and Garriochmill Way).  These investigations helped us design the required improvements for the sewer network.

Update February 2020

We are holding a second information event on 24th February at Websters Playhouse, (Upperhall Room, upstairs),  416 Great Western Road, Glasgow G4 9HZ from 5.30pm-7.30pm to discuss our sewer network improvements near the junction of North Woodside Road and Garriochmill Way will start on 2nd March 2020 for approximately 5 months. 

A short section of North Woodside Road is to be closed to through traffic during the works, pedestrian access will be maintained.

 

For documents regarding these works visit our Document hub page.