Latest update 

  • The gas diversion works are complete with final reinstatement being completed by Friday 2nd August
  • The construction works within the school have been completed and reinstatement works are being completed by the 13th August 2019
  • The remaining service diversions and further phases of work will need be planned and scheduled according to other school holiday periods

Westbank Quadrant

The work is phased over four school summers (2018-2021) to avoid disruption to the school term time.  Once complete, the new infrastructure will help prevent rags, baby wipes, plastic cotton buds, etc from overflowing into the River Kelvin during severe storm events and reduce the frequency and volume of waste water spillages in storm conditions. 

Once this summer 2019 works have been completed, the next phase will scheduled to suit school holiday periods.

 

The next phase will start again in the School Summer holidays of 2019 for 6 weeks.

Location Start Date Duration Type of work
Otago Street / Westbank Quadrant (Near Hillhead Primary School)  July 2018 6 weeks (during school summer holidays 2018)
Install chamber and pipework and headwall
Otago Street / Westbank Quadrant (Near Hillhead Primary School)  July 2019 6 weeks (during school summer holidays 2019)
Install chamber and pipework and headwall
 Otago Street / Westbank Quadrant (Near Hillhead Primary School)  July 2020

6 weeks (during school summer holidays 2020)

Install chamber and pipework and headwall
 Otago Street / Westbank Quadrant (Near Hillhead Primary School)  July 2021 6 weeks (during school summer holidays 2021 plus 4 months at end of Summer holidays to complete the project) Install chamber and pipework and headwall