Junction of Bellshaugh Gardens & Bellshaugh Road

Location Start date Duration Type of work
Junction of Bellshaugh Gardens & Bellshaugh Road  26th August 2019 10 months Install chamber, pipework and headwall

 

Update March

We are currently upgrading the storm overflow pipe, due to the severe storms and high rainfall in January and February we have been unable to work on the storm pipe and as a result of the high water levels inside the pipe the project has been extended by 2 months.

What we are doing

A section of Bellshaugh Road will be temporarily closed from 26th August 2019 for 8 months for sewer upgrade work.  A diversion will be in place via Cleveden Drive (Access to Bellshaugh Gardens to Bellshaugh Court will remain open).

Pedestrian access will be maintained at all times.

The site compound will be located on the red ash pitches adjacent to Bellshaugh Road.

Map showing the location of the temporary road closure from 23rd March until end of April 2020

160320 Bellshaugh 1 

 To get to the Scottish Mask & Puppet Centre or Bellshaugh Gardens, please follow the Diversion route below.

160320 Bellshaugh 2