Project status prepare

Through our commercial subsidiary Scottish Water Horizons we are upgrading the sewer network to accommodate the development of a new University Hospital Monklands.

At a Glance

  • Increase sewer capacity to allow new hospital to be built
  • Work to be carried out at seven strategic locations
  • Project delivered by Mackenzie Construction
  • Site investigations carried out in late 2025

Monklands Hospital Horizons Project

State-of-the-art

The work will support a new University Hospital Monklands that is being built on land in Wester Moffat in Airdrie (Pic NHS Lanarkshire)

What We Are Doing

We will be carrying out a strategic upgrade of the sewer network in and around Airdrie, Coatbridge, Bargeddie and Uddingston.

Site investigations have been carried out at seven locations which are all in wooded areas away from public roads.

Monklands University Hospital Horizons Project

Multiple Locations

The project will upgrade the sewer network at seven strategic locations (Map data ©2025 Google)

Why We Are Doing It

NHS Lanarkshire is to build a new state-of-the-art replacement for University Hospital Monklands on a site at Wester Moffat in Airdrie.

To support the new hospital, the surrounding sewer network requires upgrading.

University Hospital Monklands

Element 1 - This work will take place in a wooded area behind the Kiltarie Crescent residential development in Airdrie

University Hospital Monklands

Element 2 -  Will be taking place in land close to a domestic property, adjacent to the North Calder Water near Ardfens Road in Airdrie 

University Hospital Monklands

Element 3 - This work is taking place in a wooded area with public access path and a grassy area next to residential properties in St David’s Drive in Airdrie

University Hospital Monklands

Element 4 – We are upgrading a pipe running through woodland behind residential properties in Ross Drive, Airdrie

University Hospital Monklands

Element 5 – This work will be taking place in a wooded area between two railway lines in central Coatbridge, along from Stobcross Street (Map data ©2025 Google)

University Hospital Monklands

Element 6 - This work is taking place on private land behind the M8 motorway near to Bredisholm Road in Bailleston (Map data ©2025 Google)

University Hospital Monklands

Element 7 - This work will take place in Calderbraes Golf Club in Uddingston, between two holes on the course.

Update December 2025

As the work is mainly taking place in woodland, we have carried out a range of required environmental surveys and inspections.

These included tree aerial inspections for bats and their roosts and arboricultural surveys to assess any potential risks and determine tree management strategies.

Site investigations at all seven locations have been completed to allow detailed design and planning to be progressed.

Monklands Hospital Horizons Project

Trees have been checked for bats and their roosts

University Hospital Monklands

Arboricultural surveys have also been carried out